Peikko provided an efficient construction method for Eikonott Gland. Speed and technically advanced details convinced the total contractor Losinger-Marazzi to use Peikko's Column Connection solution. Solution consisted of HPKM®-Column Shoes and HPM® Anchor Bolts which were used in oval shape columns. 

Peikko's Column Shoes were helpful in speeding up the whole construction process. Now building seems almost like a LEGO-game.

Bertrand Faucherre, Didier Bourqui

Prosjektinformasjon

Prosjektstørrelse:
20 000 m2
Etasjer:
4
Entreprenør:
Losinger-Marazzi
Prefab produsent:
Bétontec
Levert, år:
2012
Ferdigstilt, år:
2014